Federal Clean Energy Tax Credits
What survived the 2025 tax law and by when.
The 2025 tax law (the One Big Beautiful Bill Act) changed which clean energy credits survive and for how long. Summary of the credits most projects care about, as described in public legal and tax summaries.
| Credit or technology | What changed | Key dates |
|---|---|---|
| Solar and wind (48E investment, 45Y production) | Shortened. Construction must begin by July 4, 2026, or the project must be placed in service by December 31, 2027. | Projects that start in time generally have four calendar years after the start year to be placed in service. |
| Energy storage, geothermal, hydro, nuclear and other zero-emission | Long runway kept, exempt from the solar and wind cutoff. | Full credit for construction beginning through 2033; 75 percent in 2034; 50 percent in 2035. |
| Fuel cells (48E) | Newly eligible at a flat 30 percent, with no bonus adders. | Construction beginning after 2025. |
| Foreign-entity (FEOC) material assistance | New requirement. A minimum share of equipment cost must come from non-prohibited sources. Credits cannot be sold to a specified foreign entity. | Generation: 40% (2026), 45% (2027), 50% (2028), 55% (2029), 60% (2030+). Storage: 55%, 60%, 65%, 70%, 75% (2030+). |
| Domestic content bonus (ITC) | Required percentage rises over time. | 45% for construction beginning on or after June 16, 2025 and before 2026; 50% for 2026; 55% after 2026. |
| Residential credits 25D and 25C | Ended. | After December 31, 2025. |
| New efficient homes 45L, commercial buildings 179D | Ended. | 45L for homes acquired after June 30, 2026; 179D for construction beginning after June 30, 2026. |
| EV charging 30C | Ended for new property. | Property placed in service after June 30, 2026. |
The begin-construction fight
In 2025 the IRS issued Notice 2025-42, which removed the 5 percent safe harbor for most wind and solar projects. On June 6, 2026, a federal district court in D.C. (Oregon Environmental Council v. IRS) found the notice arbitrary and capricious and vacated it nationwide, which brought back the earlier guidance: physical work of a significant nature or the 5 percent safe harbor. An appeal or new guidance is likely. The statutory July 4, 2026 date has passed, so what matters now is whether you can document that you started construction on time. Keep dated records of every step.
Summarized from public pages as of October 2026. Programs change; always confirm on the official page.