The process

Project Timeline

Which steps overlap, and what can slip.

A planning template, not a promise. Interconnection, permitting, equipment lead times and tax deadlines can move every date. Use it to see which steps overlap.

PhaseWhat happensOverlaps with
Months 0-2Goals, bills, site assessment, incentive and deadline screen, installer RFPEarly lender conversations
Months 2-4Select installer, file interconnection and incentive applications, build the capital stackCredit buyer or direct-pay planning
Months 3-6Lender underwriting, term sheets, C-PACE certification if used, contracts draftedEquipment orders
Months 5-9Closing, construction start, begin-construction documentationUtility approval to proceed
Months 8-14Construction, inspections, utility permission to operate, placed in serviceIncentive invoicing
After in-serviceClaim or sell the credit, direct-pay filing, repay bridge debt, begin monitoringTax filing season
The dates that matter most are legal, not practical: the July 4, 2026 begin-construction date and the December 31, 2027 placed-in-service date for solar and wind. Check yours with the deadline tool. Open tool →